Bankable Feasibility Study Confirms Altech’s High Purity Alumina (HPA) Project
- Published June 30, 2015 10:38AM UTC
- Publisher Wholesale Investor
- Categories Company Updates
ASX Announcement, 29th June 2015
HIGHLIGHTS
- Bankable Feasibility Study (BFS) successfully completed three months ahead of schedule
- Compelling financial and technical results:
-Capital cost estimate US$76.9 million (A$98.6million)
-Payback period 3.8 years
-Estimated pre-tax NPV of US$326.1 million (A$362.4 million) (@ 10% discount)
-Highly attractive IRR of 30.3%
-Long-term sale price forecast of US$23,000/tonne (A$25,560/tonne) for 99.99% (4N) product
-Cost of goods sold US$8,140/tonne (A$9,050/tonne)
-EBITDA of US$59.4 million (A$66.0 million) per annum - Altech will now proceed to the funding phase of the project
Altech Chemicals Limited (Altech/the Company) (ASX: ATC) is delighted to announce the positive results of its Bankable Feasibility Study (BFS) for the development of a 4,000tpa high purity alumina (HPA) processing plant at Tanjung Langsat, Johor, Malaysia and an associated kaolin beneficiation plant at Meckering, Western Australia to provide feedstock for the HPA plant (the Project).
The financial and technical outcomes from the BFS are particularly compelling and it is now the Company’s intention to move to secure the required equity and debt funding that will enable it to rapidly transition the Project to final design and development.
Total capital costs for the Project are estimated at US$76.9 million (A$98.6 million), assuming a USD:AUD exchange rate of 0.78.
Annual revenues at full production (4,000tpa of HPA) are forecast at US$92.0 million (A$102.2 million), with an assumed long-term selling price of US$23,000 (A$25,560) per tonne of HPA, FOB Malaysia. Total annual operating costs, including mining, beneficiation, shipping and processing are estimated at US$32.6 million (A$36.2 million) or US$8,140 (A$9,050) per tonne of final HPA product at full production, resulting in an impressive gross margin of ~65%.
Earnings before interest, tax and depreciation (EBITDA) are expected to be US$59.4 million (A$66.0 million) per annum at full production, the pre-tax Net Present Value (NPV) of the Project is US$326.1million (A$362.4 million) at a discount rate of 10%, and the Internal Rate of Return (IRR) is ~30.3%. Payback of capital is 3.8 years.
The Project presents a robust and attractive business case that delivers high margins, strong cash flows, and the rapid payback of a relatively modest capital investment. Having considered the results of the BFS, the Company will now proceed to secure the required funding and continue with detailed design, permitting and approvals, and subject to funding, commence the ordering of long-lead items, initiate site clearances and then commence construction.
Altech’s managing director Mr Iggy Tan said, “ The BFS was completed three months ahead of schedule, which is testament to the hard work and commitment from our BFS team”.
“The results from the BFS have confirmed the Company’s belief that the unique qualities of its Meckering kaolin deposit, combined with HCl processing to produce high purity alumina, is a technically viable and commercially attractive business case – a potential “company maker”. Subject to successful funding, the development schedule will see campaign mining commence at Meckering around Q4-2016”, he concluded.
To read the full document, please click on the link below.